Making better use of the loft
Making the bedrooms more comfortable
The homeowners wanted to keep the two bedrooms rather than change the number of rooms. The rear bedroom needed more usable space, while both rooms needed better heating and insulation.
At the front of the house, the bedroom remained beneath the pitched roof. We renewed the roof covering and insulation, rewired the room and built cupboards into the eaves. One of these cupboards also hides the underfloor-heating controls behind an access panel, so they can still be reached when needed.

Both bedrooms were fitted with wet underfloor heating, with acoustic insulation added beneath the floors. The rooms could be heated separately, rather than relying on one setting for the whole loft.

A living room above the outrigger
The new living room was built over the roof of the existing rear outrigger. The architect designed a large sliding corner window so the children could look out across the neighbouring rooftops, rather than having a conventional window on one wall.
The ceiling is another feature of the room. Instead of covering the structural roof joists with plasterboard, we left them exposed and painted them white. The roof was built with its insulation above the structural deck, so the joists could remain visible underneath.

The homeowners supplied the parquet-style timber flooring, which we fitted as part of the finishing work. With the pale timber floor, white ceiling and corner glazing, the room feels quite different from the bedrooms next door.

Making the most of the wetroom
The new wetroom sits beside the living room. Rather than dividing off the shower with a conventional square enclosure, the design uses a curved tiled wall and a movable glass screen.

The homeowners chose narrow tiles, brass fittings and a green basin. We installed the fittings and formed the shower so the floor drains towards a square outlet. An electric rooflight brings daylight into the room, while underfloor heating and a brass heated towel rail provide warmth.

The curved wall and the way the tiles meet at the corners needed particularly careful work. We’ll explain how they were built in the next section.
Living at home while the roof was rebuilt
The family stayed in the house throughout the project, but the children couldn’t use their bedrooms while the work was happening. They moved into other rooms, leaving the whole top floor available for construction.
We put scaffolding at both the front and rear of the house, with a temporary roof to keep the property protected while the existing roof was opened up. For much of the structural work, materials came in through the large front sash window. Later, when that access was no longer available, materials had to be carried through the house.
The rear dormer was largely taken down and rebuilt. At the front, we stripped the existing pitched roof, fitted a new membrane, renewed the leadwork and installed new tiles. Both bedrooms were rewired, insulated and fitted with underfloor heating before the floors and finishes went back in.
The room directly beneath the new outrigger also formed part of the works. It needed structural supports for the new room above, along with a rebuilt floor, heating, electrical work and two new windows. The family had been using it as a temporary bedroom, so they had to move out of that room too when we reached this stage.
When the structural drawings needed changing
One of the most important decisions came while we were building the new roof structure.
The engineer’s original drawings showed substantial supports running diagonally down either side of the rear dormer. They were made from thick timbers with a steel plate between them. Although they were part of the approved structural design, their position would have taken up a noticeable amount of the bedroom.
That was particularly frustrating because the old dormer already had supports restricting the space. Rebuilding it was supposed to improve that.
We were working from the drawings supplied by the homeowner’s architect and engineer, so we couldn’t simply move the supports ourselves. The issue was raised during a progress meeting, and the homeowner asked the design team to look at another way of supporting the roof.
The engineer revised the arrangement. On one side, the support was moved into the corridor so the bedroom wall could remain flush. On the other, a horizontal timber arrangement replaced the original diagonal support.
Some of the work already completed had to be undone, and the team stopped while the revised details were prepared. This coincided with the summer holidays and the homeowner being away, so there was a one-month pause before work resumed.
The construction itself took 14 weeks. The design pause added another month to the overall calendar period.
This is a useful example of why it’s worth understanding where structural supports will sit inside a finished room, not just whether the engineering works on paper.
Changing the outside from timber to zinc
The original design called for timber cladding on the new extension.
During the build, the homeowner and architect became concerned about demonstrating that the proposed timber build-up would meet the required fire standards. They decided to change the external finish to zinc instead.
The final specification was RHEINZINK Graphite, fitted using a traditional standing-seam system. The specialist package covered 70 sqm of roof and wall cladding. The zinc sections were made at the specialist’s workshop before being brought to the house and installed.

The homeowner considered continuing the zinc over the lower parts of the outrigger, but decided the extra cost wasn’t worthwhile. Those sections were finished in slate instead.

The large external windows were supplied through a specialist chosen by the homeowner. We formed the openings, prepared the surrounding structure, coordinated the installation and made good afterwards.
We also installed three electric VELUX rooflights, one in the front bedroom, one above the stairs and one in the wetroom.
The finished roof carries four solar panels. The solar installation was arranged separately by the homeowner, but we worked with the specialist and prepared the necessary cabling while the roof was being rebuilt.
Building the curved shower
The wetroom’s curved shower wall took more work than a conventional straight partition.
We formed the curve using flexible plywood, added reinforcing mesh and applied render until the surface was smooth enough for the narrow tiles. The room was then fully waterproofed before tiling began.
The tiles had to follow the curve without leaving uneven gaps. At the exposed corners, the tiler cut the edges at angles so they met neatly without separate tile trims.

We also formed the floor with a slope towards a square drain, installed the concealed plumbing and fitted the movable glass screen. The original drawings had shown a different drain arrangement, but the square outlet was used in the finished room.
Underfloor heating across the upper rooms
The homeowners chose wet underfloor heating for the two existing bedrooms, the new living room, the wetroom and the room directly underneath the outrigger.
The pipework connects back to the existing boiler in the ground-floor kitchen. Each main room has its own heating control, with the wetroom sharing a heating zone with the adjoining living room.
The controls and pipework connections are housed in the front bedroom’s eaves cupboard. We fitted an access panel so they can be reached for servicing without dismantling the storage.
This meant the homeowners could keep the bedrooms free of wall-mounted radiators while controlling the temperature in the different rooms.
Returning to investigate a leak
A few months after the project was finished, the homeowner contacted us because water was coming through at the neighbour-side edge of the new outrigger during heavy wind-driven rain.
We returned to investigate and found that deteriorated brickwork on the neighbouring side of the shared wall was allowing water through. It hadn’t previously affected an occupied room in the same way, because there hadn’t been a living space beneath that part of the roof.
Although the damaged brickwork wasn’t part of our original work, we carried out the repairs for the homeowner. No further water coming through was reported afterwards.
Ask where the structural supports will end up
A beam or roof support might look straightforward on a drawing, but its position can make a big difference to how much of the finished room you can actually use.
On this project, the original structural arrangement would have taken up space inside the rebuilt bedroom. The engineer was able to revise it, but that meant stopping work and changing part of the structure.
Before the build starts, it’s worth asking your architect or engineer to show you where the main supports will sit in the finished rooms.
Think about the stairs when adding over an outrigger
An extension above the rear outrigger doesn’t necessarily sit at the same height as the existing loft.
Here, the new living room and wetroom were lower than the children’s bedrooms, so the landing and stairs had to change.
When looking at plans for a similar extension, pay attention to the floor levels and how you’ll move between rooms, not just the amount of floor space being added.
Agree the external materials early
The original design used timber cladding, but concerns about meeting the required fire standards led to a change to zinc during construction.
That affected the specialist work needed and the final cost.
It’s worth asking your architect to establish the appropriate external materials and fire requirements before the build begins, particularly when extending close to neighbouring properties.
Plan for the rooms you’ll lose during construction
The family could stay in the house because they had other bedrooms available, but the children couldn’t use the loft throughout the work.
They also had to move out of the room beneath the new extension when we needed access to install its structural supports.
If you’re living through a loft rebuild, work out which rooms will be unavailable and where everyone will sleep before construction begins.